| 27th May
2004
ATTENDEES
| D Park |
Acting Chief
Executive |
| J H Keelty |
Director of Finance, Technology and Strategy |
| S Hartnell |
Director of Human Resources |
| J M Wilkinson |
Director of District Valuer Services |
| P Sanderson |
Director of Modernisation |
| M Morrison-Paton |
Head of Communications |
| A Grinstead |
Non Executive Director |
| |
|
| A Hudson |
|
| D Leggo |
|
| |
|
| A Mouland |
Secretary |
Council Tax Project Update
The purpose of this paper was to set the scene for the presentation
advising the Management Board on the progress and current status
of the Council Tax Revaluation 2007 programme.
The CTR 2007 Programme was working on several levels: strategic,
tactical and functional. It was aiming to deliver change into
the organisation as well as deliver the largest mass appraisal
in the world.
Reports from the VOA were channelled through the IR Centre of
Excellence. The CoE was comprised of project management experts
ensuring best practice was applied. They send monthly reports
to the Minister and quarterly reports to OGC.
The message from ODPM was to keep pushing ahead and not to let
the Balance of Funding Review divert progress from the current
preparatory tasks.
Corporate Communications had developed an outline communications
programme, which had been passed to ODPM to reflect in a comprehensive
overall communication strategy.
‘GO’ magazine had been a major success. It had become
the third most popular part of the intranet on only its third
day.
The Newcastle pilot on the use of questionnaires to collect
information had achieved a 50-60% response rate and as a result
of this success an approach was being made to the Minister to
extend their use across the network.
The AVM would provide five comparables that could be presented
to taxpayers along with the notification of banding. It was imperative
that the information shows how we got to the adjusted sale price.
The Programme Board would be considering the evidence available
to make a firm recommendation on the adoption of the AVM on 22
June 2004 based on the four criteria of timetable, taxpayer creditability,
costs and benefits and future service needs. The Management Board
would then be asked to this on 23 June before it was put to Ministers.
HR Review
The purpose of the paper was to provide the Management Board
with the results of the review into the organisation and overall
structure of the HR Directorate and to recommend options for
improvement.
Some changes had been made but problems were still being experienced.
The challenge was to improve the structure using the fixed resources
available.
Some of the recommendations could be taken forward without requiring
the approval of the Management Board but advice was required
where boundaries between divisions were crossed. All the changes
recommended could be met within the current budget.
More work was required with Groups and Units to enhance their
capabilities to enable them to be used as an additional resource.
E-HR would enable diverse strands of HR to be brought together.
The split of policy and operations within CEO HR was not helpful
in terms of providing clear lines of responsibility or end to
end process delivery. HR will restructure under the 2 Unit Heads
who would lead 7 teams focussed on combined policy and operations
subject areas.
More work on the detail of the restructuring would be carried
out and staff would be fully advised of the proposals before
recommendations were implemented.
Workforce Planning Update
The purpose of this paper, which was for information only, was
to provide the Management Board with an update of the projected
staffing need requirements for the period 2004-2010 and to examine
how the Agency’s operational needs impact on HR responsibilities
for recruitment, advancements, training and accommodation.
The paper updated the position reported to the Management Board
in March.
There were still some peaks and troughs particularly in Band
3 need but it was anticipated that further work in progress would
help mitigate these.
More thought needed be given to succession planning particularly
in the higher pay bands.
Assessment and Development Centres
The purpose of this paper was to report to the Management Board
on the results of the Assessment and Development Centres.
The new process had proved to be successful in selecting g new
Band 1 and Band 2 individuals. It was recommended that the centres
as devised and facilitated by HR, and DBM Samuell, the outside
consultants, should continue to be used to select staff for all
non-specialist roles in Bands 1 and 2.
There were some concerns over the correlation between the sift
results and candidates subsequent performance at the assessment
and development centres. The consultants were looking at devising
an improved sifting process.
There were still some vacancies at Band 2 level and there was
now a very small reserve list. Some vacancies would need to be
filled through expressions of interest. It was therefore recommended
that further Assessment and Development centres should be held
in late 2004 or early 2005.
Management Development
The existing Management Development Programmes were picking
up new Band 1 and Band 2 staff but failed to meet the needs of
Band 3 staff and graduates who had potential for management positions.
The management board decided that this issue should be covered
by the work of the newly established Management Development project
and would want to consider it further at a later meeting.
Voice Services in the VOA
The purpose of this paper was to consider whether it was the
right time to review our requirements. CGEY would take over the
existing contract from the 1 July 2004. The VOA had to ensure
that it had the voice services required to meet the needs of
the different business streams over the next five to ten years.
It was important to identify the key issues such as Council
Tax and mobile workers and to ensure that we had the infrastructure
to deal with these.
The management board decided that there should be a comprehensive
review to identify the available options. The consultancy costs
would be met out of the HR budget.
|