| 25th March 2004 ATTENDEES
| M A Johns |
Chief Executive |
| D Park |
Deputy Chief Executive, Director Local Taxation |
| J H Keelty |
Director of Finance, Technology and Strategy |
| S Hartnell |
Director of Human Resources |
| J M Wilkinson |
Director of District Valuer Services |
| P Sanderson |
Director of Modernisation |
| A Grinstead |
Non Executive Director |
| D Stathers |
Non Executive Director |
| |
|
| A Sherriff |
|
| D Hughes |
|
| K Kendrick |
|
J Berry
|
|
| |
|
| A Mouland |
Secretary |
Risk Management
The purpose of this paper was to invite Management Board members
to consider and approve the summary of VOA high-level risks.
The summary contained the top twenty risks to the VOA.
The summary of risks was re-written bi-annually and checked
and amended each year in between. This had been done at the weekly
meeting on the 11 March. The risks needed to be recorded as agreed
by the Management Board before being presented to the Audit Committee
on 26 March.
The summary of risks was discussed by the Management Board and
agreed subject to a few minor amendments.
SR 2004
The purpose of this paper was to provide further information
on the progress of SR 2004.
The paper included some judgement decisions and showed high
level figures as bids to clients. The VOA was expected to provide
these revised figures to its clients very soon. . There would
then be a further stage of review in late summer or autumn but
it was hoped that the paper gave realistic levels of contingency
and realistic bids, which were reduced from earlier estimates,
especially in the first year, providing clear evidence for our
clients that we were taking serious steps to reduce costs.
Productivity gains would vary year on year but the VOA was projecting
achieving savings of 5% per annum overall.
Geographic Information Strategy
The purpose of the paper introduced by Paul Sanderson was to
consider the VOA’s use of, and need for, geographic information
and to determine a strategy to guide the development of a geographic
information system for the VOA.
The paper followed on from the OS presentation to the MB at
the December 2003 workshop but it was necessary to have a GI
strategy statement in place before proceeding.
The Pan Government Agreement for the supply of Ordnance Survey
data provided a foundation of consistent geographic information
in the form of Mastermap. The VOA hadn’t made use of this
and required our own software to incorporate it into our database.
The benefits to the Agency were:
- GIS would become the central point for the collation
and display of data enabling the VOA to pull together the
disparate data that exists within the Agency.
- The topographical layer would allow the Agency
to carry out a matching exercise with our database particularly
in relation
to non-addressable hereditaments.
- There would be increased
flexibility with an ability
to monitor and identify changes within the landscape.
- The
accuracy of analysis and valuations would be enhanced by
access to the most current information available.
- The Agency’s
image would be enhanced by the increased quality and consistency
of data.
No cost savings were envisaged by the GI strategy although it
would enable the VOA to improve the quality of the service it
already provides.
The next step was to set out a business case covering the cost
of the software and links to the databases and also the cost
of the databases themselves.
Workforce Planning Update
The purpose of the paper was to provide an update of the need
requirements for the period 2004-2010 as requested by the Board
in January, to examine how the Agency’s operational needs
impact on HR responsibilities of recruitment, advancements, training,
accommodation and pay at a strategic level and to set out HR’s
plans to achieve the staffing levels to meet those needs.
HR informed the Board that they were more satisfied with the
short term position although they would continue to monitor the
CT situation. It was expected that 60% of valuations carried
out by the AVM would not require significant manual intervention.
Some contingency work was being done in the event of this being
amended.
There were still some peaks and troughs in Bands 3 and 4 and
there was a concern that there would be difficulties recruiting
staff for Band 3 posts. These could be smoothed through downreaching
and layering.
There was concern that DVS would suffer if there were problems
recruiting sufficient Band 3’s. HR informed the Board that
DVS posts would be filled first as this was critical.
The Board agreed that the workforce planning document should
be a dynamic document and regularly updated.
Training & Development Programme for 2004/5
The purpose of this paper was to suggest to the Management Board
how training resources should be spent in 2004/5 through the
submission of a Strategic Training and Development Plan.
The Board were concerned that the management training was focused
on new managers only. A new management development programme
scheduled for the autumn would be aimed at key new and existing
managers.
Rather than focusing management training on individual bands
the intention was to take the Group Management team as a whole
and to give them training together.
In order to drive efficiencies a Group Manager post would be
created in Training and Development Services to monitor the budget.
The efficiency target was to keep within financial limits although
a model would be produced to contain more robust measures such
as benchmarking.
It was necessary to see a payback of money invested in training
to show that efficiencies had been created throughout the network.
There was a desire to capture the resource used and benefit
gained from on the job training. TDS were looking at an evaluation
on a number of levels but were experiencing difficulties in obtaining
actual costs. DVS had included this information within their
work measurement.
Training for finance staff would be reviewed and amended to
provide a more focused package.
R2005 – Valuation Downloads
The purpose of the paper, which was for information only, was
to advise the Management Board on progress being made with the
production of 2005 valuations against target and to provide an
early indication of the effects of the revaluation.
The targets set so far had been successfully achieved with 88.86%
of valuations completed. There was still concern over the number
of valuations that have been validated.
|